| Confessions of an Architect:
Or, How I Learned to Stop Worrying and Love Partnering
by Gray Plosser, FAIA, KPS-Group, Birmingham, Alabama
Like many design professionals, Architect Gray Plosser was
skeptical of this thing called "partnering." And
like many before him, that skepticism turned to enthusiasm
once his firm was involved in a partnered project. Here are
Gray Plosser's confessions regarding his conversion to a partnering
true believer.
The job is a fast-track, design/build project: a new $26.5
million U.S. District Courthouse. As architect, we work for
the general contractor, a fine organization with which we
have completed more than $165 million in both negotiated and
bid projects. Nevertheless, this was our first design/build
project.
Our first meeting was five days after the award. There were
about 25 folks, and I looked down the agenda for something
that said "pay request procedures." Not finding
it, I came across an item entitled "partnering."
I must confess my first reaction was:
"Great, we've got to invest some more time in some touchy
feely stuff just when we've got a contractor screaming at
us about schedule, and we really need to know when we can
get paid for that $100,000 plus we've put into this thing
so far."
Having set the stage and my frame of mind at the time, let
me now explain the partnering process. Because we were working
design/build, the design team, the contracting team, and the
owner-user team participated from the outset. There were three
partnering sessions.
The first session in January, 1992, focused on establishing
personality profiles, communication styles, goals, commitments,
problem resolution techniques and self-evaluation criteria.
More important, we signed a partnership agreement which included
a mission statement for the project. Interestingly, given
the pilot nature of this program, part of the mission statement
affirmed everyone's desire to see this become a positive model
for design/build in the federal arena.
The second session in June, 1992, focused on evaluations
of progress against objectives and team-building exercises.
The key obstacles to achieving objectives were also examined.
Those that had been removed or overcome were so noted and
those that loomed new were discussed.
The third session in January, 1993, was very informal and
primarily anecdotal in nature. It consisted of stories, lessons
and reflections about the project and our personal experiences
to date.
How has partnering helped? I would like to give two specific
examples which I attribute directly to the result of our partnering
process.
The first example confronted us immediately. To achieve the
design/build fast-track schedule, it would be necessary to
substantially reorganize the design sequence and thus the
approval sequence. The owner-user would not have the luxury
of seeing completed documents before construction or even
uniformly up-to-date documents at any of the review milestones.
A new approval process was devised with simultaneous reviews
and on-board updates. The contractor was an integral part
of the review process to ensure that pricing, constructability
and scheduling objectives could be met.
As it turned out, structural design was complete and construction
underway with the architectural design just 45% complete.
The entire design team, but particularly the owner, had to
radically alter the traditional modus operandi. The potential
for frustration and high anxiety was pervasive. Extraordinary
coordination and cooperation was required in the early months
of the project.
Vitally important was explicit recognition that the documents
would not be perfect, that problems would occur requiring
timely solutions, and that commitment to the schedule required
innovative ways of working together. I do not believe that
we would have managed this particularly daunting task without
the partnering process. It gave team members the personal
rapport and trust necessary to overcome what otherwise would
have been a schedule-breaking set of circumstances.
The second example was again a design issue. The original
price was based on performance specifications developed by
the owner for finishes in various areas of the building. We
felt, based on our previous experience, that the finishes
in the public spaces and in the courtrooms themselves were
neither consistent with the expectations of the judges nor
with the dignity and the stature of the courts. This was a
sensitive area which we did not relish exposing to confrontation.
Nevertheless, we raised this issue with the owner and the
judges. It was agreed that we would submit a special finish
upgrade package for approval.
This package was ultimately approved and incorporated into
the project. Valued at over $1 million, it represented a significant
willingness by the owner to trust the design construction
team in a highly sensitive area and to act in a manner consistent
with the mission statement of the project. It also represented
a high level of trust by the contractor since this work could
have adversely affected his schedule and relationship with
the owner.
There are many other examples of how partnering helped this
project. They manifest daily in the resolution of problems,
the avoidance of conflict, and the commitment to common objectives.
Discrepancies between the solicitation and the proposal, definition
of industry standards, specified products no longer available,
personnel turnover, local labor participation, shop drawings,
labor disputes and change orders all represented opportunities
for problems, disputes and claims.
Certainly, we try to use the principles of partnering on
all projects. In part, that's why I thought we really didn't
need partnering. I was wrong. And that leads me to the "why"
of partnering.
Surely we all benefit from reducing exposure to disputes
and litigation. Administrative costs can be reduced, and because
problems are resolved cooperatively, everyone can enhance
time and cost control over the project. When parties are concentrating
on the ultimate goal rather than defensive posturing, owners
and clients benefit in the form of an improved product. Open
communication and improved working relationships create an
increased opportunity to use innovative technologies and to
develop value engineering. And finally, a cooperative approach
to construction can make a project far more rewarding and
fulfilling on a personal basis.
But ultimately, I believe that there is a very tangible and
qualitative "why," and that is profitability. Each
of the above benefits has the potential to affect productivity
and the bottom line.
|